2006
Gorkunov Holding Company (Stolichnye Ovoschi) is established to develop modern greenhouse complexes for year-round vegetable production.
2007
Gorkunov Caviar House is founded.
2007-2008
Construction begins on the Yaroslavsky and Novosibirsky Greenhouse Complexes.
2010
The Novosibirsky and Yaroslavsky greenhouse complexes are commissioned, equipped with advanced Dutch technology for year-round production.
2011-2012
Phase II of the Novosibirsky complex is commissioned in 2011; Phase III in 2012, bringing the total area to 17 ha.
In 2012, Phase II of the Yaroslavsky complex (2 ha) is commissioned.
2016
The Tolmachevsky Greenhouse Complex is commissioned. The Yaroslavsky complex is expanded.
2017-2021
Phase II of Tolmachevsky (9.4 ha) is commissioned. Construction begins on the Obskoy (6 ha) and Smolensky (16 ha) greenhouse complexes, as well as on a new complex in Crimea.
2024
A robotic potted-rose production line is commissioned at the Novosibirsky Greenhouse Complex.
2025
Russia’s first robotic orchid production complex is commissioned at the Yaroslavsky Greenhouse Complex.